(5.)10 men can prepare 20 toys in 3 days working 12 hours a day. In how many days will 24 men prepare
32 toys working 4 hours a day?
Answers
Answered by
4
Answer:
10 men x 12 hrs x 3 days = create 20 toys as output is 10x12x3 = 360 hours ÷ 20 toys = 18 hours per toy.
32 toys x 18 hours = 576 hours work divided by 24 men = 24 hours each x 4 hours x 6 days.
24 men, each will require 24 hours to complete their own quota as they work 4 hours per day x 6 days.
so the answer is 6 days.