5. 15 labours complete a work in 10 days working 6 hours per day, If 18 labours are employed
on that work and the work is to be completed in 5 days, then how many hours per day
should the work be continued?
Answers
Answer:
0
Step-by-step explanation:
Case 1 :- Total no. of hours = 15 x 6 = 90
Case 2:- Total no. of hours = 18 x 5 = 90
Hence in both cases 10 days will be required to
complete the task.
They should work for 10 hours.
Step-by-step explanation:
Consider the provided information.
According to Man, Work, Hour Formula:
M₁ men can do W₁ work in D₁ days working H₁ hours per day and M₂ men can do W₂ work in D₂ days working H₂ hours per day.
It is given that 15 labours complete a work in 10 days working 6 hours per day,
Also 18 labours are employed on that work and the work is to be completed in 5 days,
That means W₁= W₂
Substitute M₁=15, D₁=10, H₁=6, M₂=18, and D₂=5 in above formula.
Hence, they should work for 10 hours.