Math, asked by hyperzalmay, 3 months ago


5: A project of construction of a building can be completed by 150 workers in 40 days. But project
manager brought 30 more workers after 16 days. In how many days will the remaining work be

finished?​

Answers

Answered by aqeelahmed0109
6

Answer:

Step-by-step explanation:

In the second scenario after 16 days, 150 workers would have completed 150*16=2400 worker days. That leaves 6000-2400=3600 worker days remaining. If you add 30 workers, it would take 3600/180=20 days longer to complete. So, the entire project would take 16+20=36 days to complete.

Answered by pusti5324
6

Answer:

In the second scenario after 16 days, 150 workers would have completed 150*16=2400 worker days. That leaves 6000-2400=3600 worker days remaining. If you add 30 workers, it would take 3600/180=20 days longer to complete. So, the entire project would take 16+20=36 days to complete.