5: A project of construction of a building can be completed by 150 workers in 40 days. But project
manager brought 30 more workers after 16 days. In how many days will the remaining work be
finished?
Answers
Answered by
6
Answer:
Step-by-step explanation:
In the second scenario after 16 days, 150 workers would have completed 150*16=2400 worker days. That leaves 6000-2400=3600 worker days remaining. If you add 30 workers, it would take 3600/180=20 days longer to complete. So, the entire project would take 16+20=36 days to complete.
Answered by
6
Answer:
In the second scenario after 16 days, 150 workers would have completed 150*16=2400 worker days. That leaves 6000-2400=3600 worker days remaining. If you add 30 workers, it would take 3600/180=20 days longer to complete. So, the entire project would take 16+20=36 days to complete.