5. Anil, Sunil and Rajat can complete a work in 4 hours. If Anil does the job alone in 12 hours and Sunil
in 10 hours, how long will it take for Rajat to finish the job alone?
The answer will be correct, I need 5th and 6th....
Answers
Answer:
B's 5 days work =
10
1
×5 =
2
1
Remaining work =1−
2
1
=
2
1
A can finish work =15×
2
1
=7.5 days
Answer = 15
Given
Consider the total work to be 1
Anil = A
Sunil = B
Rajat = C
The work done by Anil (A) = 1
12
The work done by Sunil (B)= 1
10
The work done by Anil, Sunil and Rajat (A+B+C) = 1
4
To find
The work done by Rajat (C) = 1
x
Solution
Work done by Anil, Sunil and Rajat= Work done by Anil +Work done by Sunil + Work done by Rajat
1 = 1 + 1 + 1
4 12 10 x
Group the known terms on the right side and unknown terms on the left side
1 = 1 - 1 - 1
x 4 12 10
By taking LCM, we get the denominator 60
1 = 15 - 5 -6
x 60
1 = 4
x 60
By cross multiplication,
4x= 60
x= 15
Thus, the work done by Rajat= 15 hours