5 men can 1/3 work in 5 days then 15 men complete the same work in how many days
Answers
Answered by
1
5 men can do 1/3 in = 5days
5 men can do 1 in = 5÷1/3
= 5×3 = 15 days
1 man can do 1 = 15×3 = 45days
15 men can do in = 45/15
= 3 days (Ans)
So, 15 men can do the work in 3 days......
plz follow & mark brainliest.......