5 men do 1/3 of the work in 5 days. Then the number of days required for 15 men to complete the work
Answers
Answered by
0
Answer:
3
Step-by-step explanation:
5 men can do 1/3 in = 5days
5 men can do 1 in = 5÷1/3
= 5×3 = 15 days
1 man can do 1 = 15×3 = 45days
15 men can do in = 45/15
= 3 days (Ans)
So, 15 men can do the work in 3 days......