5. Stakeholder could be:
S1: not within the project team
S2: Outside the project team, but within the same organization
S3: Outside both the project team and the organization*
Options -
a. Only S3 is true
b. Only S1, S3 is true
c. Only S1, S2 is true
d. Only S2, S3 is true
Answers
Answered by
1
Answer:
d. Only S2,S3 is true
Explanation:
Stakeholder cannot be in any project team, because he is the part of the commietee of owners of the organization