Math, asked by vinaybedekar, 11 months ago


5) Three masons can build a wall in 6 days; two of the three
masons who can build it in 9 days, started the work and
after three days handed over the work of construction of
the wall to the third mason. In how many days did he
complete the work?

Answers

Answered by abs375628
1

Answer:

3/2 ........…........is really right answer