5 workers can do a specific task in 12 hours. If the time is decreased to 8 hours how many more workers will be required? (Hint : Round off your answer to nearest whole number)
Plz tell with solution
Answers
Answered by
1
Answer:
8 workers
Step-by-step explanation:
worker required to do in 1 hr is 12×5=60
workers required to do work in 8hrs = 60÷8=7.5(8 approximately)
please mark me brainliest