Math, asked by singhshivalika3206, 1 year ago

6. 40 men are employed to finish a work in 48 days. but it is found that in 24 days only 1/4 work is done. how many more men are required in order to finish the work in time? (a) 24 men (b) 16 men (c) 22 men (d) 20 men

Answers

Answered by Anonymous
6
25 men can complete 1313 work in 24 days

Suppose xx men can complete 2323 work in 12 days

25×2413=x×1223 25×24=x×122 x=10025×2413=x×1223 25×24=x×122 x=100

Required extra men =100−25=75=100−25=75

Sabrinanathalia: u frm ?
sana468: thnks rrjack29 could u plse suggest something to score more in maths
sana468: plse its a request
Answered by shreeya589
0
the required extra men is 75
Similar questions