6. 40 men are employed to finish a work in 48 days. but it is found that in 24 days only 1/4 work is done. how many more men are required in order to finish the work in time? (a) 24 men (b) 16 men (c) 22 men (d) 20 men
Answers
Answered by
6
25 men can complete 1313 work in 24 days
Suppose xx men can complete 2323 work in 12 days
25×2413=x×1223 25×24=x×122 x=10025×2413=x×1223 25×24=x×122 x=100
Required extra men =100−25=75=100−25=75
Suppose xx men can complete 2323 work in 12 days
25×2413=x×1223 25×24=x×122 x=10025×2413=x×1223 25×24=x×122 x=100
Required extra men =100−25=75=100−25=75
Sabrinanathalia:
u frm ?
Answered by
0
the required extra men is 75