6. 45 men can plough a field in 36 days. How many men will be needed to plough it in 81 days?
a. 20 men
b. 15 men
c. 16 men
d. 24 men
Answers
Answered by
1
Answer:
c.16 men
bbhjvdfghhhgggghj
Answered by
1
Answer:
a. 20 mens
Step-by-step explanation:
M¹D¹ = Work
-M= members
- D = days or time
45 men can do a work in 36 days
to find total work , 45 * 36 = 1620 work
same work will be done in 81 day i.e., same field
let's take no. of men as X need for 81 day ,
X * 81 = 1620
X = 20 mens