6. A can complete a work in 12 days and B can complete the same work in 8 days . What part of the work will they all together complete in 1 day .​

Answers

Answered by canmshihora
1

Answer:

Both work together  for one days

=20.83 %

Step-by-step explanation:

A complete a work in 12 Days

Per days percentage work = 1 /12 =8.33 %

B Complete a work in 8 Days

Per days percentage work = 1 /8 =12.5 %

Both work together  for one days

= 8.33+12.5=20.83 %