6 carpenter working 7 hour a day can complete 20 table in 20 days how many days will 12 carpenter work 6 hours a day take to complete 36 tables
Answers
Answered by
5
6 carpenter working 7 hour a day can complete 20 table in 20 days
Total man-hour needed for 20 table = 6 × 7 × 20
(1 man-hour = 1 man working 1 hour)
Total man-hour needed for 1 table = 6×7×20 / 20 = 6×7 = 42 hours
man-hour needed for 36 tables = (36×42) hours
we have 12 carpenter who work 6hrs a day
number of days = (36×42) / (12×6) = 21 days
Answer: They need 21 days
Total man-hour needed for 20 table = 6 × 7 × 20
(1 man-hour = 1 man working 1 hour)
Total man-hour needed for 1 table = 6×7×20 / 20 = 6×7 = 42 hours
man-hour needed for 36 tables = (36×42) hours
we have 12 carpenter who work 6hrs a day
number of days = (36×42) / (12×6) = 21 days
Answer: They need 21 days
Answered by
17
6 carpenter working 7 hour a day can complete 20 table in 20 days
Total man-hour needed for 20 table = 6 × 7 × 20
(1 man-hour = 1 man working 1 hour)
Total man-hour needed for 1 table = 6×7×20 / 20 = 6×7 = 42 hours
man-hour needed for 36 tables = (36×42) hours
we have 12 carpenter who work 6hrs a day
number of days = (36×42) / (12×6) = 21 days
Answer: They need 21 days.
HOPE SO IT WILL HELP.......