6 men and 8 boys can do a piece of work in 7 days while 8 men and 12 boys can do the same work jin 5 days. How long would it take one boy to finish the same piece of work? (with solution)
Answers
Answered by
1
Answer:
Suppose 1 man alone can finish the work in x days and 1 boy alone can finish it in y days.
Then , 1 man's 1 day's work = 1x.
And, 1 boy's 1 day's work = 1y
8 men and 12 boys can finish the work in 5 days
⇒ ( 8 men's 1 day's work ) + ( 12 boy's 1 day's work ) =15
⇒8x+12y=15
⇒8u+12v=15 ... (i), where 1x=uand1y=v
Again, 6 men and 8 boys can finish the work in 7 days
⇒( 6 men's 1 day's work) + ( 8 boy's 1 day's work) =17
⇒6x+8y=17
⇒6u+8v=17 ... (ii)
On multiplying (i) by 3, (ii) by 4 and subtracting the results, we get
4v=(35−47)=135⇒v=1140⇒1y=1140⇒y=140
On putting v=1140 in (ii), we get
6u=(17−8140)=12140⇒u=(12140×16)=170
⇒1x=170⇒x=70
∴ one man along can finish the work in 70 days,
and one boy alone can finish the work in 140 days.