Math, asked by mithilesh90060otj35y, 1 year ago

6 men can complete the electric fitting in a building in 7 days how many days will it take 21 men to do the job

Answers

Answered by Keshav5318
207
Number of days required by 6 men to complete the work = 7

Number of days required by 1 man to complete the work = 7 × 6

Number of days required by 21 men to complete the work = 42/21 = 2

Hence, 2 days is required by 21 men to complete the work

===========================================


Hope it helps :-

:-)
Answered by rashi7632
46

Answer:

2 days

Step-by-step explanation:

if 6 men can do a piece of work in 7 days

°.°1 men can do a piece of work in = 6×7

.°.21 men can do the work in = 6x7/ 21

= 2days

Similar questions