Math, asked by sius, 1 year ago

6 men can complete the electric fitting in a building in 7 days how many days will it take 21 men to do the job

Answers

Answered by shubham14173
4
21 men will complete the job in 2 days
6men=7days
1men=6×7days
21men=6×7÷21
=2days

shubham14173: mark me as a brainliest
Answered by ritikkumar3
5
In days
6 man do work in 7 days then
1 man do in in 6×7
21 man do it in = 6×7
------
21
= 2 days