6 men can complete the electric fitting in a building in 7days. How many will it take21 men to do the job?
Answers
Answered by
13
6 man complete the work in 7 days..
total work = 7 ×6= 42
now man = 21
so time taken =42/21
= 2days
total work = 7 ×6= 42
now man = 21
so time taken =42/21
= 2days
Answered by
1
Answer:
2 days.
Step-by-Step Explanation:
→ 6 men can complete the electric fitting in a building in 7 days. So,
→ 21 men can do the job in days. So,
We get,
If the number of men will increase, So, the number of days for the job will decrease. Hence, here is inverse proportion.
Since in inversely proportional term, where x and y has two variations,
Where, k is a constant term.
Here,
x :-
y :-
Therefore,
Hence, 21 men can do that job in 2 days.