6 men can whitewash a building in 5 days.if 18 men are employed,find how many such buildings can be whitewashed in 5 days
Answers
Answered by
20
Given,
6 men can whitewash 1 building in 5 days.
So, 1 man can whitewash 1/(6*5) buildings in 1 day.
So, 18 men can whitewash (18*5)/(6*5) buildings in 5 days
= 18*5/6*5 = 3.
So, 3 buildings can be whitewashed.
If this answer helped you, please mark as the brainliest
Answered by
28
----------------------------------------
Here is the solution:
----------------------------------------
6 men can whitewash a building in 5 days
⇒ 6 men = 1 building
Find the number of buildings 1 man can whitewash in 5 days:
6 men = 1 building
1 man = 1/6 building
Find the number of buildings 18 men can whitewash in 5 days:
1 man = 1/6 building
18 men = 1/6 x 18 = 3 buildings
Answer: 18 men can whitewash 3 buildings in 5 days