Math, asked by shuklavidushi6724, 1 year ago

6 men or 10 women can do a piece of work in 24 days .how long will 12 men and 10 women take to finsih the work.

Answers

Answered by TiwariVaishnavi
1
Men = 6 and Women = 10

First converts men into women so we have 10/6×12 = 20 women

Total women = 20 + 10 = 30....

so According Question :

Womens. Work
10. 24 days
30. X days

: So it is a case of Inverse Variation ...

=10×24 days = 30 × X days

240= 30x

=X = 240/ 30

X= 8 days ....

So 30 women will take 8 days to finish the work.

Hope it Helps you!!

Thanks!!