6 people can do a piece of work in 8 days how long will it take for 12 people to 6 people can do a piece of work in 8 days how long will it take for 12 people to do the same piece of work? Please explain the logic behind it ​

Answers

Answered by kaushiknutbolt11
1

Answer:

kkggkklĺkjhhui77654688ihhhgggdfii

Answered by gauravkumar1301gk
8

Answer:

4 days

Step-by-step explanation:

6 people take 8 days

so, 1 person will take 6×8 days

hence 12 persons will take 6×8/12=4 days

this is because 1 man will take more time to do the same work as 6 people can do