6 person can complete electric fittings in a building in 7days how many days will it take if 21 persons do the same job
Answers
Answered by
3
6 persons=7 days
1 person=7/6
21 persons =7/6*21
so 21 persons can do it in 7/6*21
1 person=7/6
21 persons =7/6*21
so 21 persons can do it in 7/6*21
vinay177:
sorry that ansr is wrong
Answered by
3
Answer:
2 days.
Step-by-Step Explanation:
→ 6 men can complete the electric fitting in a building in 7 days. So,
→ 21 men can do the job in days. So,
We get,
If the number of men will increase, So, the number of days for the job will decrease. Hence, here is inverse proportion.
Since in inversely proportional term, where x and y has two variations,
Where, k is a constant term.
Here,
x :-
y :-
Therefore,
Hence, 21 men can do that job in 2 days.