Math, asked by govindsingh20690, 1 year ago

6 warkers can do white wash of a house
in 35 days. How many more workers will
have to be increased to complete this
work un 14 days?​

Answers

Answered by udaykiran55
0

Answer:

2

Step-by-step explanation:

6=35days

?=14(×multiplication)

6×14=?×35

?=6×14/35

2.4(approx)