6 workers can paint a hospital in 18 days working 9 hours daily. To complete the work in
12 days, how many more workers should be employed if there is no change in working
hours?
Answers
Answered by
1
Answer:
Mark me brainliest if helped Buddy!
Attachments:
Answered by
0
Answer:
As we know that if the number of workers increases then number of days decreases so they are inversely proportional to each other....
6/x=12/18
x=9 workers
Hope you are satisfied with the answer
PLEASE MARK AS BRAINLIEST