60 men could complete a piece of work in 250 days . They worked together for 200 days . After dat the work had to be stopped for 10 days due to bad whether . How many more men should be engaged to complete the work in time ?

Answers

Answered by Deepsbhargav
0
hey "15" is the correct answer

explain..

60 men can finish a work in 250 days.

1 man can finish the work in = 15000 days.

60 men worked for 200 days.

the amount of work done is 200*60=12000 days

the pending work = 15000-12000=3000 days
work is stopped for 10 days.

remaining number of days = 250-200-10=40 days.

work done by 60 men in 40 days = 60*40=2400 days

Pending work = 3000-2400= 600 days.

Let x be the additional number of workers required.

Then 40x=600=>

x=15.