60 men dig a Canal 2000 metre long in 20 days how many men required to dig a Canal 4200 long in 15 days
Answers
Answered by
1
here you go
if you like it follow me and punch that like button in the face
Attachments:
Similar questions
Math,
6 months ago
Math,
6 months ago
Math,
6 months ago
Psychology,
11 months ago
Social Sciences,
11 months ago
Political Science,
1 year ago