1) If P and Q together can complete a job in 3 days while P
alone can do the same in 12 days, then how many days
would be required by Q to do the job alone?
A) 3 days
B) 4 days
C) 6 days
D) 12 days
Answers
Answered by
1
Answer:
d po
Step-by-step explanation:
sana makatulong