7. A and B can finish a work in 30 days. They
worked for it for 20 days and then B left. The
remaining work was done by A alone in 20 more
days. A alone can finish the work in ​

Answers

Answered by AB1012
4

Step-by-step explanation:

A+B's 20days work=1/30×20=2/3

remaining work= 1-2/3=1/3

now 1/3work is done by A in 20days

the whole work done by A = 20×3=60days