7. Estimate the quantity of earthwork from the
following data :
15
Road width = 10m, Side slopes = 1.5:1 in cutting
and 2:1 in banking, Length of chain is 30m.
Chainage
RL of GL
| 20 | 21 | 22 | 23 |
71.20 71.2570.90 171.25
Chainage
RL of GL
24
70.80
25
70.45
26
70.20
27
70.35
Chainage
| RL of GL
28 29
69.10 | 69.45
30
69.70
Formation level = 70.00m, Upward gradient 1 in
200.
Answers
Answered by
2
Answer:
7. Estimate the quantity of earthwork from the
following data :
15
Road width = 10m, Side slopes = 1.5:1 in cutting
and 2:1 in banking, Length of chain is 30m.
Chainage
RL of GL
| 20 | 21 | 22 | 23 |
71.20 71.2570.90 171.25
Chainage
RL of GL
24
70.80
25
70.45
26
70.20
27
70.35
Chainage
| RL of GL
28 29
69.10 | 69.45
30
69.70
Formation level = 70.00m, Upward gradient 1 in
200.
Step-by-step explanation:
Similar questions
Computer Science,
5 months ago
Hindi,
5 months ago
Science,
5 months ago
India Languages,
11 months ago
Science,
11 months ago
Math,
1 year ago
Chemistry,
1 year ago
English,
1 year ago