7. Sachin can finish a piece of work in 24 days. He started the work but left after 6 days. His friend
Mohit agreed to finish the work for him and took 9 days to complete the remaining work. Find
the number of days in which Mohit could have finished the entire work alone.
Answers
Answered by
0
Answer:
15 is the correct days hetook