70 men can finish a piece of work in 48 days how many men will be needed to finish in 12 days
Answers
Answered by
12
Mark as Brainliest ........
If 70 men can finish a piece of work in 48 days, how many men will be needed to finish it in 12 days?
Work = rate x time
One Man can finish ’M' units of work in one day.
70 men worked for 48 days.
Work done = 70 x 48
The same work is done in 12 days.
Work done = M x 12
M x12 = 70 x 48
M = (70 x 48)÷ 12
M= 280
280 Men required to finish it in 12 days.
Ans : 280 men.
IBoss:
Brainliest
Answered by
4
70 men can finish a work in 48 days
Let the men needed to finish the work in 12 days be x.
men :- 70 x
days:- 48 12
70×12= 48×x
70×12÷48= x
x = 280
Let the men needed to finish the work in 12 days be x.
men :- 70 x
days:- 48 12
70×12= 48×x
70×12÷48= x
x = 280