Math, asked by AksNema5467, 1 year ago

8. 40 men can complete a work in 40 days. how many complete days is required to complete the work if after every 10 days 10 men joins

Answers

Answered by Sunnychodary
0
answer is 61.3333...................

paarth25: if men will join tim will decrease not increase
paarth25: time
Sunnychodary: sorry
Answered by paarth25
0
I am not sure though but I have done this

40−(40÷(10÷8.64)) = 5.44 = 6 complete days

paarth25: i meant 8.6
paarth25: 8.4
paarth25: ihave done with 8.4