8. 8 men can finish a piece of work in 40 days. If 2 more men join them, the work will be
completed in
{a) 30 days
(b) 32 days
(c) 36 days
(d) 25 days​

Answers

Answered by rituskmg
2

Answer:

pls mark me as brainliest if you are satisfied

Explanation:

8 men  take 40 days to finish

If two more men join then total number of men =  10  

8 men finish the work in =40 days

1 man will finish the work in =40×8 days          [1 man will take longer to finish the work that's why we use multiplication]

10 men will finish the work in =  

10

40×8

​  

=32 days                [10 man will finish the work faster that's why we use division]