8 man complete a work in 6 hours in how many hours will 12 men complete the same work


sneha060804: Hey friend your answer is 4 hours
AnanyaAna123: Is my calculation is wrong or else the whole process is wrong!

Answers

Answered by AnanyaAna123
6
8 men=6 hours
12 men =x
[cross multiple]
8×x=12×6
x=12×6/8
x=9 hours
Therefore 12 men complete the work in 9 hours

HOPE THIS HELPS YOU BUDDY ✌️
IF YOU LIKE IT PLEASE MARK IT AS BRAINLIEST

AnanyaAna123: Sneha are you there?
sneha060804: Yeah
sneha060804: I m
sneha060804: Look I was write
AnanyaAna123: Now understood
sneha060804: Ok
AnanyaAna123: How can you be write Sneha
sneha060804: Sry I didn't understand
AnanyaAna123: Ok
sneha060804: Ok??
Answered by siasword
4
if 8 men in 6 hrs then 12 will surely in 9 hrs.