8 men and 12 can finish a piece of work in 10 days while 6 men and 8 boys can finish it in 14 days find the work done by men and boy

Answers

Answered by Anirudhbhardwaj01
2

Step-by-step explanation:

10 ( 8m + 12 b) = 14 ( 6m + 8b)

2b = m

Therefore,

10 ( 8m + 6m) = 1

140 m = 1 & 280 b = 1

1 man needs 140 days

1 boy needs 280 days

Answered by Anonymous
1

Step-by-step explanation:

There we can see,,,

8 men and 13 women can do finish a lot of work in 15 days and work also done by men