8 men and 12 can finish a piece of work in 10 days while 6 men and 8 boys can finish it in 14 days find the work done by men and boy
Answers
Answered by
2
Step-by-step explanation:
10 ( 8m + 12 b) = 14 ( 6m + 8b)
2b = m
Therefore,
10 ( 8m + 6m) = 1
140 m = 1 & 280 b = 1
1 man needs 140 days
1 boy needs 280 days
Answered by
1
Step-by-step explanation:
There we can see,,,
8 men and 13 women can do finish a lot of work in 15 days and work also done by men