Math, asked by poojakumar1064, 1 year ago

8 men can complete a work in 14days they started the work and after 2days 2men left in how many days will the work be completedby the remaining men

Answers

Answered by sharonr
0

Remaining work will be completed in 16 days.

Solution:

It is given that 8 men can complete a work in 14 days. Thus the total work is 8 x 14 = 112

Work done by 8 men in 2 days = 8 x 2 = 16

Remaining work = 112 - 16 = 96

Now it is said that after 2 days 2 men left. Remaining men = 8 - 2 = 6 men.

Thus 6 men will complete the remaining work i.e. 96 in 96/6 = 16 days.

Thus the remaining work will be completed in 16 days.

Learn more about time and work

7 men can complete a work in 12 days. They started the work and after 5 days two men left. In how many days will the work be completed by the remaining men?

https://brainly.in/question/6679445

A and B can finish a piece of work in 16 days and 12 days respectively. A started the work and worked at it for 2 days. He was then joined by B. Find the total time taken to finish the work.

https://brainly.in/question/2584306

Answered by Fatimakincsem
0

It will take 16 days to complete the remaining work.

Step-by-step explanation:

Given data:

  • Number of men = 8
  • Days = 14

Solution:

Total work done =  8 x 14 = 112

Work done by 8 men in 2 days = 8 x 2 = 16

Remaining work = 112 - 16 = 96

We are given that after 2 days 2 men left.

Remaining men = 8 - 2 = 6 men.

Thus 6 men will complete the remaining work i.e. 96

Work completed by 96 men =  96/6 = 16 days.

Hence the remaining work will be completed in 16 days.