8 men can do a piece of work in 20 days. In how many days
could 20 men do same work?
A.6 b.8 C.4 d.10
Answers
Answered by
5
Answer:
Answer. Step-by-step explanation: 8 days are required to complete the work by 20 men.
Attachments:
Answered by
2
Answer:
8 days
Step-by-step explanation: