8 men complete a piece of work in 12days . 4women alone can complete the same work in 48days and 10 children alone can complete the piece of work in 24 days .In how many days can 10men , 4women and 10children together complete the piece of work
Answers
Answered by
4
in my opinion the right answer is 36