8 men complete the wok in 15 days. If 4 men more added then how many days
are required to complete the same work?​

Answers

Answered by shrivastavarrishita
1

Answer:

Here is your answer dude

Step-by-step explanation:

8 men can do a piece of work in 15 days

1 man can do a piece of work in 15*8 days

20 men can do a piece of work in 15*8/20 days = 6 days

20 men do the same work in 6 days.