8 Men completes a work in 10 days. how long will 10 men will take to complete the same work ​

Answers

Answered by PraaneshNair
1

Answer: 8 days

Step-by-step explanation:

=> Given;

Time taken for 8 men = 10 days

=>Time taken for 1 man = 10 * 8 days

Hence 1 man will take 80 days.

=> Time taken for 10 men = (time taken for 1 man)/ 10

= 80/10

= 8 days.

Hope it helped!

Please do consider marking the answer as brainliest and rating it!

(For being the first to answer, with accurate results)

Answered by arvindkumar3188484
0

Step-by-step explanation:

Let,

X1 = 8men

Y1 = 10days

X2 = 10 men

Y2 = ?

Using,

X1Y1 = X2Y2

8*10 = 10*Y2

80 = 10*Y2

80/10 = Y2

8 Days = Y2

so answer is 8 days