8 men working for 9h a day complete a piece of work in 20 days.in how many days can 7 men working for 10 h a day to complete the same piece of work
Answers
Answered by
1
8x9x20=1440 person-hours to complete the work
7x10=70 person-hours a day
1440/70=20.57
7x10=70 person-hours a day
1440/70=20.57