Math, asked by NayonJakaria, 5 months ago

8 people can do a job in 12 days. What percentage will it take to complete the work by reducing 2 people?​

Answers

Answered by OppaiSugoy
0

Answer:

16 days

Step-by-step explanation:

8 person do the job in 12 days

So per day job of those 8 people is 1/12

Now if 2 people are reduced, work done in 1 day by 6 people be let say is X

8 : 1/12

6 : 1/X

after cross multiplying

8/X = 1/2

1/X = 1/16

After inverting, we get X = 16

So 6 people can do the same work in 16days