9. A man works for 10 hours in a day and completes a job in 16 days. In how many days will he complete
the same job if he works for 8 hours in a day
Answers
Answered by
0
Answer:
21
Step-by-step explanation:
I think this is the answer but I am not sure
Answered by
4
Answer:
20 days
Step-by-step explanation:
Time worked = 10 hours
Time taken to complete work = 16 days = 384 hours
Work done = 10 × 384
Time worked = 8 hours
Time taken to complete work = x
Work done = 8 × x
= 480 hours or 20 days