9 labourers can complete the construction of a wall in 18 days. how many less days will 12 laboures take to complete the same wall?
Answers
Answered by
3
Hi user,
Please Mark it brainliest plzzzz
Attachments:
Anonymous:
Ab bolo
Answered by
10
Answer:
Step-by-step explanation:
If the number of lobourers increases ,the days taken to construction the wall decreases in same proportion.
Clearly , number of labourers varies inversely to the number of days.
Therefore.,
•••♪