9. Sushma tan do embroidery on a saree in 15 days, Raveena can do the same job in 10 days. iney worked
together for 2 days and then Raveena left and Sushma completed the remaining work. How many days
did Sushma take?
Answers
Answered by
4
Riya can embroidered saree that is left by Vineeta in 10 days