92 people can complete a job in38 days.in how many days will 46 persons complete the same job?

Answers

Answered by urvi434
14
CONCLUSION÷
1.(The maximum number of people can complete their work in less days).
2.(The minimum people can complete their work in maximum days).



92 people can complete work=38 days (given)
46 people can complete work=?days.

92 people can completework=38 days
1 person can complete=38×92
1 person can complete =3496

46 people can complete work=3496/46
=76


46 people can complete their work in 76 days.