a A and B individually can do a work in 8 hours and 12 hours respectively. A worked first for 2 hours and then left. How long will B take to finish the remaining part of the work ?
Answers
Answered by
0
Answer:
B will take 3 hours to finish the remaining part of the work
Step-by-step explanation:
Let the quantity of the work is x unit.
To do this complete work A will take 8 hours and B will take 12 hours.
A worked for first 2 hours and then left.
∴ Remaining quantity of the work is 2x/8=x/4 unit.
B does x unit work in 12 hours
B does x/4 unit work in 12x/4x = 3 hours