A alone can complete a work in 16 days and b alone in 12 days starting with a they work alternate days
Answers
Answered by
0
14 5/8
Step-by-step explanation:
A=16days & B=12days
LCM of 16 & 12 is 48
Now, 16/48=3 ,12/48=4
A's one day work 3 unit & B's one day work 4 unit in 2 days 7 unit of work completed
In 1=(1×2)days(2×7)=14 unit of work completed
In (1×3)=3days(7×3)=21days unit completed .............
In (2×7)= 14days (7×7) =49 unit completed remaining 5 unit work completed in 5/8 days
Hence work is completed in 14 5/8