A alone can complete a work in 48 days and b alone can complete the same work in 72 days. A, b and c together can complete the same work in 24 days. What will be c's per day payment if he is paid rs. 72000 to complete the entire work alone ? (in rs.)
Answers
Answered by
0
Answer:
Rs.500/-
Step-by-step explanation:
effeciency of A = 1/48
effeciency of B = 1/72
given combined effeciency of A,B&C together = 1/24
=> effeciency of C alone = 1/24 - (1/48 + 1/72)
= 1/24 - (3/144 + 2/144)
= 1/24 - 5/144
= 6/144 - 5/144
= 1/144
=> No. of days taken by C alone to finish the work = 144 days
payment for the 144 days = Rs. 72000
=> payment of C per day = Rs.72000/144
= Rs.500/-