A alone can do a piece of work in 10 days and B alone can do it in 15 days. In how many days will A and B together do the same work ? (1 Point) 5 days ,6 days ,8 days​

Answers

Answered by cubesolver310
0

Answer:

6days please mark it brainliest

Answered by chxcykoo
0

Answer:

  \huge \mathfrak \pink{given}

A can do the piece of work in 10 days

B can do that piece of work in 15 days

 \huge  \mathfrak \pink{to \: find}

In how many days the work can be done by them together?

  \huge \mathfrak \pink{solution}

Number of days A required to do the piece of work = 10 days

Number of days B required to do the piece of work = 15 days

  \tt \: work \: done  \: by\: a \: in \: 1 \: day \:  =  \frac{1}{10}

 \tt \: work \: done \: by \: b \: in \: 1day \:  =  \frac{1}{15}

Work done by both (A + B) together =

 \huge \frac{1}{10}  +  \frac{1}{15}  =  \frac{10}{60}  = \frac{1}{6}

(take out the LCM )

 \blue{ -  -  -  -  -  -  -  -  -  -  -  -  -  -  }

\boxed{they \: can \: do \: the \: work \: in \: 6day}