A alone can do a work in 9 days,whereas B can do it in 18 days. If they work together, then the work will be completed in,
Answers
Answered by
1
Step-by-step explanation:
Work done by A in one day = 1/9
Work done by B in one day= 1/18
So,Work done when both A and B work on the same task for one day= (1/9)+(1/18) = 1/6
Concluding,
If 1/6th part of work is done by both in one day then they will require 6 days to complete the task fully
For example if you have to write a full page and you write half of it in one day then you will require 2 days to write full page
So,A and B will require a total of 6 days to complete the work if they work together.